amc422 said:
Calculate is set to "automatic". I initially only entered % complete in the
"% Physical Complete" column. Then I went back and entered % complete for
each task in the "Task Information - General" tab, in the % complete box. I
thought this would correct the problem but it did not.
Any ideas?
Thanks,
Anna
Anna,
Maybe I'm taking your post too literally but you mention that % Complete
is not "rolling up" to the Summary Line. In Project % Complete values do
NOT roll up, rather, they are calculated by Project using the formula:
Summary % Complete = [sum of performance subtask Actual Durations]/[sum
of performance subtask Durations] x 100%. A similar formula is used for
% Work Complete. If you are expecting the % Complete or % Work Complete
to be some other value at a Summary Line, try using the above formulas.
If % Complete on your Summary Lines is zero and one or more of the
performance subtasks have non-zero values (assuming the subtasks are not
zero duration milestones) and Calculation is set to automatic, you might
try running Detect and Repair (Help/Detect & Repair).
Hope this helps.
John
Project MVP