B
BK
Let's say I have a project that will last 2 days. The first day, I 'plan'
the project (it takes all day, I am the resource). The next day, I have 4
contractors working on their pieces of the project, all which will take one
day, running concurrently.
The project lasts 2 days, and there is 5 days worth of work. After the
first day, the project time is 50% complete, but I still have 80% of the
project (the 4 contractors) to be completed. MS Project tells me I'm 20%
complete, and this makes sense to me. However, I have to report this
'discrepancy' to some micro-managing superiors, on a much more complex
project. Is there a graph which would display this for me graphically? I'm
looking for a graph which compares 'project days' to 'cumulative work
content'. Or is this the Holy Grail of project management?
BK
the project (it takes all day, I am the resource). The next day, I have 4
contractors working on their pieces of the project, all which will take one
day, running concurrently.
The project lasts 2 days, and there is 5 days worth of work. After the
first day, the project time is 50% complete, but I still have 80% of the
project (the 4 contractors) to be completed. MS Project tells me I'm 20%
complete, and this makes sense to me. However, I have to report this
'discrepancy' to some micro-managing superiors, on a much more complex
project. Is there a graph which would display this for me graphically? I'm
looking for a graph which compares 'project days' to 'cumulative work
content'. Or is this the Holy Grail of project management?
BK