D
David Oliver
It seems MSP uses % complete rather than % work complete
to compute earned value from planned value for a task or
project. This doesn't make sense to me given that
planned value is work X resource rate and %complete is
really a measure of duration rather than work. It's like
comparing apples and oranges. Using %complete instead of
%work complete also really skews the earned value on
partially completed tasks that have been split during
schedule statusing (Tools/Tracking/Update
Project/Reschedule uncompleted work to start after...)
So I am wondering if MSP provides a configuration option
that allows you to use %work complete to compute earned
value (BCWP), and consequently spi and cpi? Can anyone
help with that?
to compute earned value from planned value for a task or
project. This doesn't make sense to me given that
planned value is work X resource rate and %complete is
really a measure of duration rather than work. It's like
comparing apples and oranges. Using %complete instead of
%work complete also really skews the earned value on
partially completed tasks that have been split during
schedule statusing (Tools/Tracking/Update
Project/Reschedule uncompleted work to start after...)
So I am wondering if MSP provides a configuration option
that allows you to use %work complete to compute earned
value (BCWP), and consequently spi and cpi? Can anyone
help with that?