Joe said:
What is the difference between the columns "% Complete" and "% Work
Complete"? Why would you use one versus the other? All input is
appreciated...
% Complete is just measuring how much of the total duration has passed,
and is pretty useless. It would mean something if the work effort over
the duration of the project was linear, which it very rarely is. % Work
complete is how many of the total work hours scheduled have been
completed, which is much more useful. Of course, it's only useful if
your effort estimates are accurate. If it's taking you twice as many
hours to do the tasks as you originally planned, % Work Complete might
look pretty good, until you figure out that everything's taking longer.
That's why Earned Value is so useful.
Hope this helps in your world.