Completed tasks no longer show any detail on the task name

R

RichT

Some tasks for which I've marked as complete no longer show any detail on the
task name while some do. I have been searching the application to figure out
what happened, and how I can view this detail again, but have had no luck so
far.

The other scary part of this is that when I attempt to change one of these
blank tasks from 100% completed to 0% to try to see if this resolves it, that
shuts down my application. This doesn't happen when I edit a cell that's
complete with text visible.

Has anyone experienced this? And even better, anyone know how to resolve
it? Thanks for any help!
 
J

Jan De Messemaeker

Hi Rich,

It looks like the file is corrupted.
You can try (sorry, the word is try) the trick described in FAQ 43 (sse URL
of FAQs in my signature)
HTH
 
R

RichT

Hi Jan,

I tried your suggestion, but it didn't work or change my
blank completed tasks. This file doesn't appear that large to me
compared to another newer project I have created of similar size, and
compared to other older project files that are huge. Any other ideas would
be a great help. Thanks!
 
J

Jan De Messemaeker

Hi,

Rather than guessing, can you send me the file?
jandemesATprom-adeDOTbe
Greetings,
 
R

RichT

Hi Jan,
Thank you for the help. I am sorry that I can't send you the file. It
contains info which I am not allowed to share. I have found out that I am
able to edit the blank task cell with another task name and it will let me
move the completion from 100% to 0%. I do not remember what the cells
contained originally. I hope you can go from this. Any help I can get or
other ideas would be great! Thanks!
 

Ask a Question