R
Russ Parrish
I am using Project to coordinate a staff of 50 people spread across 15
tasks. Most everyone on the team is assigned to multiple tasks
depending on their skills and the needs of the tasks. I ask the team
leads for each task to give me the percentage of time required for
each person in order to meet their scheduled delivery dates. I don't
hold our staff to 100% allocation so that I can determine how many
people short we are. I do this by exporting my data to excel then
computing the number of full time people required to perform the work
indicated by the percentages of time required according to the task
leaders. I can then compare the work required to our actual staff
size to find the short fall.
I would like to find a way in MS PRoject to roll up the number of
resources required to accomplish the work rather than the extra work
of importing the data into Excel then having to convert all of the
percentages from text to number (essentially requires re-entering)
before I can then insert the sum functions to calculate the totals for
each task then roll that up to a total number for the entire team.
Is there a way to create a column in Project that would do the
calculation I'm looking for. I know how to create custom fields
(columns) and enter formulas etc but I have not been able to figure
out how to reference other columns and specific rows. I'd like to
total the precentages to whole numbers for each task then total all of
the task totals to a team total.
I hope my explanation is clear I'm not a MS Project expert by any
stretch of the imagination and may not be using the correct
terminology.
Thanks
Russ
tasks. Most everyone on the team is assigned to multiple tasks
depending on their skills and the needs of the tasks. I ask the team
leads for each task to give me the percentage of time required for
each person in order to meet their scheduled delivery dates. I don't
hold our staff to 100% allocation so that I can determine how many
people short we are. I do this by exporting my data to excel then
computing the number of full time people required to perform the work
indicated by the percentages of time required according to the task
leaders. I can then compare the work required to our actual staff
size to find the short fall.
I would like to find a way in MS PRoject to roll up the number of
resources required to accomplish the work rather than the extra work
of importing the data into Excel then having to convert all of the
percentages from text to number (essentially requires re-entering)
before I can then insert the sum functions to calculate the totals for
each task then roll that up to a total number for the entire team.
Is there a way to create a column in Project that would do the
calculation I'm looking for. I know how to create custom fields
(columns) and enter formulas etc but I have not been able to figure
out how to reference other columns and specific rows. I'd like to
total the precentages to whole numbers for each task then total all of
the task totals to a team total.
I hope my explanation is clear I'm not a MS Project expert by any
stretch of the imagination and may not be using the correct
terminology.
Thanks
Russ