Hey! Hoping for some guidance. In Project, I have three WBS deliverables,
all of which are being worked on by the same resource at the same time. When
any one of these is finished, I want the resource to begin working on WBS
deliverable #4. So, the predecessor of 4 is 1, 2 and 3, but the start date
of #4 should vary, depending on which is finished first: 1, 2 or 3.
In Excel, it'd be easy. I'd just say something like START-4 = MIN(FINISH-1,
FINISH-2, FINISH-3).
Hopefully, I've explained that clearly.
Thanks!