D
DavidC
Hi,
I am explaining why a schedule submitted by a contractor would not achieve
the end date.
The contractor had a calendar set for 12 hours per day, seven days per week,
but set the options to 10 hours oper day, 56 hours per week.
Clearly this has caused the problem.
Trying to explain why this casued a problem to non project users is now my
task.
What I want to confirm is that the setting in options sets the work
associated to a task, and that work is then applied to the calendar, which
determines whether or not the work can be done within the available time
availbe to carry out the work.
Is this a reasonable explanation to use to non project users? They are
nonetheless engineers and Project Managers so will understand the concepts.
Many thanks
DavidC
I am explaining why a schedule submitted by a contractor would not achieve
the end date.
The contractor had a calendar set for 12 hours per day, seven days per week,
but set the options to 10 hours oper day, 56 hours per week.
Clearly this has caused the problem.
Trying to explain why this casued a problem to non project users is now my
task.
What I want to confirm is that the setting in options sets the work
associated to a task, and that work is then applied to the calendar, which
determines whether or not the work can be done within the available time
availbe to carry out the work.
Is this a reasonable explanation to use to non project users? They are
nonetheless engineers and Project Managers so will understand the concepts.
Many thanks
DavidC