Hello,
Looking for some help re consolidated projects...
Currently building a master project that has 10 - 12 sub projects inserted.
Each of the sub projects is controlled by a separate scheduler. The master
is controlled by the lead scheduler. If an update is made in one of the
sub-projects, is there any way to stop update of master project until
proposed changes are approved by the lead scheduler? Do not want automatic
update of data until cause / effect is determined. Any help would be
appreciated
regards,
Duane
Looking for some help re consolidated projects...
Currently building a master project that has 10 - 12 sub projects inserted.
Each of the sub projects is controlled by a separate scheduler. The master
is controlled by the lead scheduler. If an update is made in one of the
sub-projects, is there any way to stop update of master project until
proposed changes are approved by the lead scheduler? Do not want automatic
update of data until cause / effect is determined. Any help would be
appreciated
regards,
Duane