P
pjelliott
I have a few projects that I need to consolidate into a master project.
At present, some of these use different calendars (e.g. one uses a 7-day
working week while the others use a 5-day working week).
If I insert these into a consolidated project to manage my resources over
multiple projects, how will project deal with the different calendars? Will
this cause problems with the overall master project?
I'm using Project 2007 SP2.
Many thanks
Kind regards
Peter
At present, some of these use different calendars (e.g. one uses a 7-day
working week while the others use a 5-day working week).
If I insert these into a consolidated project to manage my resources over
multiple projects, how will project deal with the different calendars? Will
this cause problems with the overall master project?
I'm using Project 2007 SP2.
Many thanks
Kind regards
Peter