Consolidated Resources

E

ECD

I created a shared resources file. Once linked, I expected the drop-down
file in each of my linked projects to link to the shared resources. Instead,
the drop-down in my file shows only those that I originally entered directly
into a file. Did I do something wrong? Is this the way it is supposed to
work? If so, how does this help? Thanks for your help.
 
J

Jan De Messemaeker

Hi,

The pool has to be open as well if not the project file ignores the other
resources in the pool.
HTH
 
E

ECD

I do get a message as I open my project file that asks me to open the pool
file. I respond yes and still am unable to see the shared resources.
Thoughts?
 
J

Jan De Messemaeker

Hi,

After you say yes, does the pool open?
If not, its address in the file may be wrong (have you moved any of the 2
files?)
HTH
 
E

ECD

The pool does open as read only. I am going in task information -- selecting
resources and clicking on the drop-down. I still only get the ones that I
originally entered into the initial file. Thoughts?
 
J

Jan De Messemaeker

Hi ECD,

That ws not the drop-down I understood.
When you go to Gantt Chart, Resource Names Column, the drop-down should show
all resources in the pool.
Also, Resource sheet should show all resources.
Task Usage, whatever you do, only and always shows the resources assigned to
a task. If there's only one resource assigned to a task, clicking the + is
showing only one resource.
This is not meant to be a dropdown of all resources but a detail on the
resources on THAT tasks.
Hope this helps
 