H
hornet50
I have inherited a group of stand alone programs that I have consolidated
into a master program. Many of these programs have hard constraints assigned
to the tasks from the various schedule developers by assigning dates to the
start or finish columns. Can I safely go in and change / remove the
constraints if the tasks are completed or at least an actual start date has
been assigned without affecting other tasks in my schedule?
Thanks in advance for your assistance.
Hornet50
into a master program. Many of these programs have hard constraints assigned
to the tasks from the various schedule developers by assigning dates to the
start or finish columns. Can I safely go in and change / remove the
constraints if the tasks are completed or at least an actual start date has
been assigned without affecting other tasks in my schedule?
Thanks in advance for your assistance.
Hornet50