T
Tomhad
Hi
I really need some help with this. I have been using MSProejct since before
Windows and recently upgraded to 2003 Standard.
Firstly, I discovered by accident that the outlining function on the as
shipped version was not working properly and updated to SP2. (is this the
latest ???)
Now however, I am experiencing another major issue
After setting up a list of tasks with dependencise and then trying to
outline using keyboard short cuts or the mouse. MSP IS BREAKING LINKS ! even
though I have Autolink switched on
This is a real problem , thankfully it was not a big schedule but it
resulted in almost all of my links being lost or out of order !
It can be replicated by doing the following:-
Set up a three actvity schedule ABC etc, outline them under an "overall" task
Gantt shows three linked tasks with a summary, then try to move a task up or
down, the links are broken ???
This is definitly a bug, It does the opposite to what it says it does, it
does not keep the links it breaks them !!How do I get it fixed ? any one
know. ?
I am not interested in work arounds (even if there are any, it takes me too
much time already fixing MS's poor quality software) the software should
behave the way it says it does ? How can I report it to MS ?? any one know ?
This is a real nuisance
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/communitie...a484-0221ccb17af5&dg=microsoft.public.project
I really need some help with this. I have been using MSProejct since before
Windows and recently upgraded to 2003 Standard.
Firstly, I discovered by accident that the outlining function on the as
shipped version was not working properly and updated to SP2. (is this the
latest ???)
Now however, I am experiencing another major issue
After setting up a list of tasks with dependencise and then trying to
outline using keyboard short cuts or the mouse. MSP IS BREAKING LINKS ! even
though I have Autolink switched on
This is a real problem , thankfully it was not a big schedule but it
resulted in almost all of my links being lost or out of order !
It can be replicated by doing the following:-
Set up a three actvity schedule ABC etc, outline them under an "overall" task
Gantt shows three linked tasks with a summary, then try to move a task up or
down, the links are broken ???
This is definitly a bug, It does the opposite to what it says it does, it
does not keep the links it breaks them !!How do I get it fixed ? any one
know. ?
I am not interested in work arounds (even if there are any, it takes me too
much time already fixing MS's poor quality software) the software should
behave the way it says it does ? How can I report it to MS ?? any one know ?
This is a real nuisance
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/communitie...a484-0221ccb17af5&dg=microsoft.public.project