Hi Bupp,
A slight variation on Mike's answer to Yvonne should give you what you
need. Assuming the working time for your workday is 8:00 am to 5:00
pm -- the task cannot be started any later than 2:00 pm on any Monday
through Friday to allow it to finish by 5:00 pm.
Create a new calendar (Tools > Change Working Time, New). In the new
calendar select Monday through Friday by clicking the column heading and
edit the working time to 7:59 am to 1:59 pm. Insert a one minute
duration task as a predecessor linked finish to start with 3 hour task
Apply the new calendar to the one minute duration task. Because of the
predecessor relationship, your 3 hour task can now only be scheduled
between 8:00 am and 2:00 pm.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project