PRJ 2K3 Standard:
Hello all.
How do i create a stoplight chart that would show resources allocated above
50 hours (say...out of 60 total hours) a defineable week and resources that
are only allocated 40 hrs a week. Basic resource (over/under) allocation
report.
I understand that PRJ uses max units in % numbers to designate assignment,
but I was going to create a custom [number3] field to capture the number and
then do graphical indicators. But since its in max units, it wouldn't
apropriate to use.
Do I need to calculate a formula in [number3] that converts the [max units]
#'s to hours or is there a field that I can directly use? Help.
Thanks in advance.
Mathmatically-impaired (NYC)
Hello all.
How do i create a stoplight chart that would show resources allocated above
50 hours (say...out of 60 total hours) a defineable week and resources that
are only allocated 40 hrs a week. Basic resource (over/under) allocation
report.
I understand that PRJ uses max units in % numbers to designate assignment,
but I was going to create a custom [number3] field to capture the number and
then do graphical indicators. But since its in max units, it wouldn't
apropriate to use.
Do I need to calculate a formula in [number3] that converts the [max units]
#'s to hours or is there a field that I can directly use? Help.
Thanks in advance.
Mathmatically-impaired (NYC)