Hi Jim,
You don't mention which version of Project you are using but in Project 2003
on the Analysis toolbar there is a Copy Picture to Office Wizard which steps
you through the process. If you don't have Prj 2003, I agree with Joel's
recommendation. Set up the view (Gantt chart etc.) how you want it to appear
and use the Copy Picture button on the Standard toolbar. If you have more
tasks than fit on a single screen you can select all tasks before clicking
the Copy Picture button to capture more tasks than appear.
Hope this helps. Let us know how you get along.
Julie