S
sushrutj
The MS Project 2007 file was created with work days. Now i want to
convert them to calendar days - how do i do this?
thanks.
convert them to calendar days - how do i do this?
thanks.
Hi, I have a similar problems, however the issue is different.
I have already entered all the tasks and their durations in the
duration field. By default, Project used the Standard calendar (5 work
days) and all the durations are calculated in work days. So for example,
if I have a 6 day task it will be 8 calendar days. Now I want to convert
these durations in calendar days but without changing the numbers of the
durations and only reschedule them. So for example, if the 6 day task
previously had been starting on 04.01.2010 and ended on the 11.01., now
I want it to end on 09.01. (Saturday). I tried this by creating a new
calendar with a 7 day work week. Is this the right way?
--
MalkiaSashko
------------------------------------------------------------------------
MalkiaSashko's Profile:http://forums.techarena.in/members/149228.htm
View this thread:http://forums.techarena.in/microsoft-project/773756.htm
http://forums.techarena.in
Hello,
Yes, this helped. I created a new base calendar with 7 work days.
However, since the dates of all tasks must be calculated based on the
already entered durations, I applied the new base calendar to the whole
project. Thank you for the quick reply.
--
MalkiaSashko
------------------------------------------------------------------------
MalkiaSashko's Profile:http://forums.techarena.in/members/149228.htm
View this thread:http://forums.techarena.in/microsoft-project/773756.htm
http://forums.techarena.in
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.