Adrian
A colleague has provided me with a schedule that is demonstrating some weird
behaviour in the cost field.
There are a number of tasks where the cost field is not correct. For example
there is a task with a single resource assigned that is zero percent
complete. the resource rate is £71/hr and the work for the task is 5 hours
yet the cost field shows £644.80 and not the £355.00 that would be expected.
When I do a slit view and show the resource costs in the bottom window it
puts £355 against the single resource.
If anyone can provide an explanation for this I would really appreciate it?
Cheers,
behaviour in the cost field.
There are a number of tasks where the cost field is not correct. For example
there is a task with a single resource assigned that is zero percent
complete. the resource rate is £71/hr and the work for the task is 5 hours
yet the cost field shows £644.80 and not the £355.00 that would be expected.
When I do a slit view and show the resource costs in the bottom window it
puts £355 against the single resource.
If anyone can provide an explanation for this I would really appreciate it?