Hi,
I can't but repeat the same thing.
The cost in week 3 is the difference between the cum cost after week 3 and
the cum cost after week 2.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Peter" <
[email protected]> schreef in bericht
ok,
But, I'm not looking for the cost over the whole period of the
project.
For
example, if I have a project that has been in progress for 5 weeks,
and I
want to know the cost incurred during week 3. How would I go about doing
this. The project is in week 5 but I want to know the costs during
week
2?
Peter
"Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in
message
Hi,
Cost over a certain period is the difference between Cum Cost (an
available
timescaled field) on end and start date of the period.
If you can export that?
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Peter" <
[email protected]> schreef in bericht
Hi,
Yes I know about that option, but I'm looking for the ability to
filter
by
cost over a certain period. I want to use this in an export. What I'm
trying
to do is generate an invoice report for a specific period and not for
the
entire project. So I need to be able to have cost only totaled for
a
given
period.
Peter
Hello Peter,
Use the Task Usage view : View / Task Usage
and insert the Cost field : Right clic on a yellow cell...
Hope this helps,
--
Gérard Ducouret [Project MVP]
"Peter" <
[email protected]> a écrit dans le message de
Hi,
I'm trying to figure out how I can set a filter up that would allow
me
to
see the cost of tasks for a certain time range. The date filter
does
not
seem to do this, but is always applied across the entire
project.
Does
anyone know how to setup a date filter that would filer the cost
also?
Peter