J
JPD
I notice when I mark a task complete .. the cost will go to zero.
This is causing a little bit of a problem for me since we do not have
a solid baseline and may never have one. This is a constant changing
program where I need to calculate planned cost on "work packages".
This cost sometimes includes task that have completed and some task
that may have dates that changed from a "baseline".
So I guess the question is does cost always go to zero when a task is
complete? so my only option is to try and stay on top of updating
task on this moving "baseline"
This is causing a little bit of a problem for me since we do not have
a solid baseline and may never have one. This is a constant changing
program where I need to calculate planned cost on "work packages".
This cost sometimes includes task that have completed and some task
that may have dates that changed from a "baseline".
So I guess the question is does cost always go to zero when a task is
complete? so my only option is to try and stay on top of updating
task on this moving "baseline"