L
Laz
Using MS Project Standard 2007, I have a 500 +/- line project plan with
several summary tasks. I developed the costs for each non-summary task and
would expect that the costs sum up to each summary task. Though this seemed
to be working I noticed the summary task costs did not always sum to what I
would expect.
I went thought the process of checking cost entry for ever row, they were
correct. Then I manually added the costs (I used and export to Excel). The
sums on the Excel spreadsheet were different then in Project and they were
the sums I was expecting.
How do make sure the calculations are correct?
Is there a recalculate function for the cost column in Project similar to
Excel? I looked but could not find it. Or is there perhaps a patch for MS
Project Standard 2007?
several summary tasks. I developed the costs for each non-summary task and
would expect that the costs sum up to each summary task. Though this seemed
to be working I noticed the summary task costs did not always sum to what I
would expect.
I went thought the process of checking cost entry for ever row, they were
correct. Then I manually added the costs (I used and export to Excel). The
sums on the Excel spreadsheet were different then in Project and they were
the sums I was expecting.
How do make sure the calculations are correct?
Is there a recalculate function for the cost column in Project similar to
Excel? I looked but could not find it. Or is there perhaps a patch for MS
Project Standard 2007?