T
Tom
What's the best way to assign cost of labor to the actual time it takes to
complete a task while still showing the possible duration of the task? In
other words, what if a task only takes 1 min to complete, but may take a week
before the task is acted upon. In project, you have to specify the date when
that task is expected to be performed. Is it possible to set a one week
duration (best guess to when task will actually be performed) and only assign
a cost ($/hr) to the actual time it takes to complete the task? Hope i didn't
confuse anyone
complete a task while still showing the possible duration of the task? In
other words, what if a task only takes 1 min to complete, but may take a week
before the task is acted upon. In project, you have to specify the date when
that task is expected to be performed. Is it possible to set a one week
duration (best guess to when task will actually be performed) and only assign
a cost ($/hr) to the actual time it takes to complete the task? Hope i didn't
confuse anyone