J
Jrufin
Hi,
I would like to assign a task to a "group" of person instead of assigning it
to a specific persons. For example instead of assigning a task for the 3
person (George, Bob, Steve) to complete, can I assign it to a "Draftsmen"
group instead?
If that is possible the working hours per day of this "Draftsmen" group
should be 8x3= 24hrs per day, right? Because currently if I assign a task to
an entity named "Draftsmen" it will show to be overallocated (they are
assigned to some other tasks), but in reality it must not be the case because
there are 3 person in that "Draftsmen" group working in total of 24hrs per
day. Project is interpreting that this "Draftsmen" group is only 1 perosn
doing 8hrs/day work! Please help!
Thanks.
I would like to assign a task to a "group" of person instead of assigning it
to a specific persons. For example instead of assigning a task for the 3
person (George, Bob, Steve) to complete, can I assign it to a "Draftsmen"
group instead?
If that is possible the working hours per day of this "Draftsmen" group
should be 8x3= 24hrs per day, right? Because currently if I assign a task to
an entity named "Draftsmen" it will show to be overallocated (they are
assigned to some other tasks), but in reality it must not be the case because
there are 3 person in that "Draftsmen" group working in total of 24hrs per
day. Project is interpreting that this "Draftsmen" group is only 1 perosn
doing 8hrs/day work! Please help!
Thanks.