I tried creating a customer calendar for a summary tasks. When I applied it
the duration and date remained the same. I expected the date to get earlier
since I created a calendar for 7 days a week of work instead of 5 days a week
of work.
I also wanted the remaining project to be stanadrd calendar. How can I
accomplish this and check to make sure the change actually works?
the duration and date remained the same. I expected the date to get earlier
since I created a calendar for 7 days a week of work instead of 5 days a week
of work.
I also wanted the remaining project to be stanadrd calendar. How can I
accomplish this and check to make sure the change actually works?