create custom calendar

T

TechArch

I tried creating a customer calendar for a summary tasks. When I applied it
the duration and date remained the same. I expected the date to get earlier
since I created a calendar for 7 days a week of work instead of 5 days a week
of work.
I also wanted the remaining project to be stanadrd calendar. How can I
accomplish this and check to make sure the change actually works?
 
M

Mike Glen

See my previous answer. You will note than any calendar changes you make
will only affect data entered in the future. You'll need to re-enter the
Durations.

Mike Glen
Project MVP
 
G

Gérard Ducouret

Hi TechArch ,
Apply your custom calendar to the subtasks, not to the summary.

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top