Create Project calendar that goes from night to next day?

J

Jimbo53

I was trying to establish a shift calendar from 11pm to 7am. Project gave me
an error message that said the finish time must be later than the start time.

How do you set-up a calendar that goes from the evening of one day into the
morning of the next day?
 
J

JulieS

Hi Jimbo53,

The working time on a day cannot cross midnight. So if you have a shift
that starts Monday night at 11:00 PM you'll need to change the times as below:

Monday From 11:00 PM To: 12:00 AM
Tuesday From 12:00 AM to Lunch/Dinner break time.
From Lunch/Dinner break To 7:00 AM
From 11:00 PM to 12:00 AM

And so on.

Hope this helps. Let us know how you get along.
 