M
MAR1114
In MS project 2003 we have difficulty link items from various subproject,
since the row is treated as a summary line when the subproject is inserted.
In order to link it would be nice to set a predecessor by link and line item
in link.
e.g. (1-354) as a predecessor would allow you to link multiple subprojects
and by specific line...
1= Line the Subproject in one (Summary) and 354 is the specific line in the
subproject. Multiple link (1-354,1-360,2-150) as predecessors.
If there is a way to do this already, then please let me know.....
since the row is treated as a summary line when the subproject is inserted.
In order to link it would be nice to set a predecessor by link and line item
in link.
e.g. (1-354) as a predecessor would allow you to link multiple subprojects
and by specific line...
1= Line the Subproject in one (Summary) and 354 is the specific line in the
subproject. Multiple link (1-354,1-360,2-150) as predecessors.
If there is a way to do this already, then please let me know.....