Critical Path Missing

S

Steve House

Do you have the Gantt chart formatting set to show the critical tasks in a
distinctive colour? What do you see in the network diagram?
 
R

richard.craven

BHoward said:
Tasks with zero slack are not shown as on the critical
path

Are you looking at "Free Slack" or "Total Slack"? A task can have no "Free
Slack" but still not be on the Critical Path.

ie. 3 1 day tasks have to be done in a 5 day period. Logic says task 2
follows task 1 and task 3 follows task 2. So when the programme is first put
together task 1 starts on Monday with the idea being task 3 finishes on
Wednesday. Task's 1 and 2 will have no "Free Slack" but task 3 will have 2
days "Free Slack". All tasks will have 2 days "Total Slack".

"Total Slack" is what defines the Critical Path of the Programme.

Hope this helps

Richard
 