Mti said:
I have tasks that do not show up in the Critical Path but always want them to
be included. How can I force a task to be included in the Critical Path?
This is for project leaders who must manage to the critical path. Thanks!
Mti,
You need to explain to project leaders that just because a task doesn't
show up on the critical path, it is still part of the plan and must be
accomplished. If they are just managing to the critical path, the
overall project will either not get done, or will take a lot longer
simply because tasks that are not on the path will not get done
(assuming only "managed" tasks are worked), and eventually they will
become critical. In the meantime, more efficient effort to perform them
will have passed and the team will always be in crisis mode - a poor
management style.
I suggest you review the critical path on a regular basis because
critical path tasks represent the bottlenecks that are slowing down
progress on the plan. Just don't forget to work the tasks that are not
in trouble.
However to answer you basic question, use a spare flag field to identify
those tasks you want included and then create a modified critical path
filter. Have it look for the flag AND all tasks that have "0" or less
Total Slack.
Hope this helps.
John
Project MVP