Cross-project dependencies

A

Andrew K

I've linked a task in Project A to a task in Project B as predecessor. When
I view either project by itself, MSP nicely displays the
predecessor/successor relationship by greying task names. When I consolidate
the two projects into a plain insert-the-projects "master" or into a
pooled-resources master, I no longer see the relationships. Of course I can
insert columns showing the predecessors/successors, but is there a graphical
way to display them?
 
J

Jan De Messemaeker

Hi,

AFAIK, they are drawn on the gantt Chart the same way as ordinary links.
HTH
 
A

Andrew K

Thanks, Jan. I spoke too soon -- the master does in fact show the links in
grey. We can close this thread.
 