I am managing a system implementation...
We have three separate 2-day conference room pilots (CRP) we want to host to
test the system.
At each of these CRP's, 50% of the attendees will spend all day (8 hours
each day) for the full 2 days, while the other 50% will spend a 1/2 day (4
hours) the first day and a 1/2 day the 2nd day.
All I want is to be able to do is nail this down to two days (i.e. it is
very high priority) but at the same time have the schedule reflect the hours
that each participant is required to spend each day.
I am using leveling to resolve over-allocations but it just seems to really
muck this up for the CRP. I feel like I have tried everything (priority,
don't level assignments, fixed duration, don't split).
Ideas?
Thanks, Kevin
We have three separate 2-day conference room pilots (CRP) we want to host to
test the system.
At each of these CRP's, 50% of the attendees will spend all day (8 hours
each day) for the full 2 days, while the other 50% will spend a 1/2 day (4
hours) the first day and a 1/2 day the 2nd day.
All I want is to be able to do is nail this down to two days (i.e. it is
very high priority) but at the same time have the schedule reflect the hours
that each participant is required to spend each day.
I am using leveling to resolve over-allocations but it just seems to really
muck this up for the CRP. I feel like I have tried everything (priority,
don't level assignments, fixed duration, don't split).
Ideas?
Thanks, Kevin