Hi, I´ve just upgraded to 2007 and something that has always worked in 2003
is not working anymore.
In Task Usage View I add a Custom field. Suppose I add Text1 custom field.
In Resource Usage View I add Text1 custom field.
For assignemnt rows , the values used to be linked, that is Assignment.Text1
is the same value for the same assignment both in the Task Usage and
Ressource Usage.
In Project 2007 are completely unlinked.
(I-m not tryng to see a task value in a resource, we al lknow taht is not
possible, dont we! . I´m just talking about assignments.)
Thanks
is not working anymore.
In Task Usage View I add a Custom field. Suppose I add Text1 custom field.
In Resource Usage View I add Text1 custom field.
For assignemnt rows , the values used to be linked, that is Assignment.Text1
is the same value for the same assignment both in the Task Usage and
Ressource Usage.
In Project 2007 are completely unlinked.
(I-m not tryng to see a task value in a resource, we al lknow taht is not
possible, dont we! . I´m just talking about assignments.)
Thanks