We have several users who we dont want to give full Project Pro 2007 to as
they will only be creating Activities with one or two tasks. These means we
can use the web based Activity creation features. Custom Fields appear in
the Summary of the Activity, but I can see anyway of entering data into the
Tasks custom fields, is this possible?
they will only be creating Activities with one or two tasks. These means we
can use the web based Activity creation features. Custom Fields appear in
the Summary of the Activity, but I can see anyway of entering data into the
Tasks custom fields, is this possible?