Hi John,
thanks for your reply. I have not quite understoode what you mean
(could be my english or my project skill etc.; could you maybe
specifically tell me the where in the menue i will find it, since i am
using a german version). So I am trying to be more specific with an
example:
1. The project plan looks like this
Task Work Resource
--------------------------------------------------------------------------
------------------------------------------------
Design phase 15
design part a 7
getting information 3 Tom[33%], Anne[33%], James[33%]
consolidating infos 1 Tom[50%], Anne[50%]
working on design 3 James[50%], Anne[50%]
desgin part b 8
getting information 3 Tom[3%], Anne[33%], James[33%]
consolidating infos 2 Tom[50%], Anne[50%]
working on design 3 James[50%], Anne[50%]
now i like to have a table/report like this:
Level 2 Taks Resource Work
(aggregated work of level three tasks)
--------------------------------------------------------------------------
---------------------------------------------------------
design part a Tom 4,5
desgin part a Anne 3
desing part a James 2,5
design part b Tom 5
desgin part b Anne 3,5
desing part b James 2,5
thank you.
Hi there,
I am trying to come up with a report like this (these are the columns):
task resource work .... .....
Well the clue is that I like to have only tasks on level two and the
work per resource should be aggregated from the lower levels.
Could anybody please help me with this.
Thks in advance. I really appreciate any help.
stpauli,
Just looking at your proposed report columns I suggest you take a look
at one of the usage views, probably the Task Usage view. Does it have
what you need, or at least close enough?
As far as your clue is concerned, I guess I'm just not a good detective
because I have no idea what you "like" to have. Sherlock is not one of
the MVPs. Please try that one again.
John
Project MVP