joyce said:
I need a report or I need to create some type of printout which consist of
resource names, task names and finish times. However I have to limit the
finish time has to be within a two week timescale.
joyce,
It's not real clear exactly what you want the report to look like but it
sounds like the Resource Usage view, (which really displays resource
names and resource assignments), might be a starting point. You could
then apply the Date Range filter for a two week time span. Note: if you
don't need the timescaled data (right side of view), just drag the
vertical separation bar to the extreme right.
If that doesn't do it, then we will need a more complete explanation of
what type of report you want before we can suggest an alternate approach.
John
Project MVP