customizing a view (project

J

joyce

I need a report or I need to create some type of printout which consist of
resource names, task names and finish times. However I have to limit the
finish time has to be within a two week timescale.
 
J

John

joyce said:
I need a report or I need to create some type of printout which consist of
resource names, task names and finish times. However I have to limit the
finish time has to be within a two week timescale.

joyce,
It's not real clear exactly what you want the report to look like but it
sounds like the Resource Usage view, (which really displays resource
names and resource assignments), might be a starting point. You could
then apply the Date Range filter for a two week time span. Note: if you
don't need the timescaled data (right side of view), just drag the
vertical separation bar to the extreme right.

If that doesn't do it, then we will need a more complete explanation of
what type of report you want before we can suggest an alternate approach.

John
Project MVP
 
D

DavidC

Hi Joyce,

You will need to do the following:

1 You will need to set up a filter that looks at all finish dates that are
less than now plus two weeks.

2 Set up a new table with just the task name, reosurce names and finish dates

3 Create a new report through custom reports and based on the table from
above, and using the above filter.

Hope this helps you.

regards

DavidC
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top