Date Format on Gantt Chart

S

Stevan

Hello,


I am trying to show complete date next to milestone on the Gantt Chart, but
it appears only day and month (dd/mm). How to show complete date dd/mm/yyyy ?

Regards,


Stevan
 
J

JulieS

Hi Stevan,

See Format > Layout in the menu. This will allow you to select the date
format for the milestones.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top