Can anyone advise how to change date formats in Porject 2007. I have created
a project plan and the task dates display in the gannt view. I have gone into
options and changed the view to show date / time but this does not show in
this view. Is this possible or can anyone csuggest what I am doing wrong.
 
J

JulieS

Hello Kevin,

I imagine the table definition is over-riding the Project definition.
Choose View > Tables, More Tables. Select the table you have
currently applied to the Gantt chart view (most likely Entry) and
click the Edit button. In the Table Definition dialog box, set the
date format to "Default" to revert back to the date format specified
in Tools > Options.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top