Hi all,
Usually I have my projects set in the Options to show the date/time format
as that: "Date & Time (short format)".
Lately I've been doing "Job Plans" that span only 8 hours or less and the
man in charge would like to see only the time in the Start column, which is
easy to set in the Options set up, but then when I go back to a regular
project I have to re-set the option to date/time again.
Is there any way I can use a Start1-10 column and show only the time?
i.e. Extract the time from the Start date/time using a formula.
TIA, Colin D.
Usually I have my projects set in the Options to show the date/time format
as that: "Date & Time (short format)".
Lately I've been doing "Job Plans" that span only 8 hours or less and the
man in charge would like to see only the time in the Start column, which is
easy to set in the Options set up, but then when I go back to a regular
project I have to re-set the option to date/time again.
Is there any way I can use a Start1-10 column and show only the time?
i.e. Extract the time from the Start date/time using a formula.
TIA, Colin D.