DavidC
Hi,
Has anyone no what might be causing this intermitent fault. I have a
schedule with links to other schedule files, and I use the 'soft' links to
set dates for tasks which do not lend themselves to being summary tasks and I
need to create a specific report.
What I have noted is:
1 When I open the file, the soft links do not automatically refresh but go
to some other spurious dates which really screw up the report. I then have
to select all the soft links and update them. Yet I have selected the option
for these to be automatically updated rather than being asked to update links.
2 When I add a new task into the schedule and link it, it retains the date
used by default as the start date, but never refreshes when the link is
added, nor when recalculated. I then ahve to close the schedule and the
programme and reopen then it gives the correct date.
Any thoughts please
Regards
DavidC
Has anyone no what might be causing this intermitent fault. I have a
schedule with links to other schedule files, and I use the 'soft' links to
set dates for tasks which do not lend themselves to being summary tasks and I
need to create a specific report.
What I have noted is:
1 When I open the file, the soft links do not automatically refresh but go
to some other spurious dates which really screw up the report. I then have
to select all the soft links and update them. Yet I have selected the option
for these to be automatically updated rather than being asked to update links.
2 When I add a new task into the schedule and link it, it retains the date
used by default as the start date, but never refreshes when the link is
added, nor when recalculated. I then ahve to close the schedule and the
programme and reopen then it gives the correct date.
Any thoughts please
Regards
DavidC