Has anyone seen this? Something happened between this week and last week. I
update my actuals and realign the hours remaining (and finish dates) manually
on a weekly basis. To my surprise, when I opened the Resource Usage View I
noticed that instead of seeing a weekly date of 1/4/2009 - I see a weekly
date of 1/4/2010! I checked for the same in the Task Usage view - yup; off
by 1 year. HOWEVER - the dates in the Tracking Gantt and Gantt view are
right on the money. Any thoughts about this?
I consider myself to be an expert user and have only seen this once before
on a colleage's MS Project file.
Running MS Project 2003 (SP3) - stand alone with no interfaces or custom
macros.
Peter
 
M

Mike Glen

Hi Peter,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 1. on fiscal years

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 

Ask a Question