Bev Ferris
since moving onto MPP 2003 I have been experience problems with task start
and end dates. for expample I create a task which starts on 29/09 (as a start
as soon as possible/no Lag days) is is a 30 day task , MPP calculates it
finish as 04/11. I caluclate it finsh as being 07/11. I have checked all my
resource calenders and have non working weekends with no resource non
availability during this time. Task are se tto Fixed duration. This is
happening on a lot of the tasks across all of my Plan.. so It must be some
setting that I am missing - Any ideas????
and end dates. for expample I create a task which starts on 29/09 (as a start
as soon as possible/no Lag days) is is a 30 day task , MPP calculates it
finish as 04/11. I caluclate it finsh as being 07/11. I have checked all my
resource calenders and have non working weekends with no resource non
availability during this time. Task are se tto Fixed duration. This is
happening on a lot of the tasks across all of my Plan.. so It must be some
setting that I am missing - Any ideas????