Dates withink project don't agree with Actual calender days

B

Bev Ferris

since moving onto MPP 2003 I have been experience problems with task start
and end dates. for expample I create a task which starts on 29/09 (as a start
as soon as possible/no Lag days) is is a 30 day task , MPP calculates it
finish as 04/11. I caluclate it finsh as being 07/11. I have checked all my
resource calenders and have non working weekends with no resource non
availability during this time. Task are se tto Fixed duration. This is
happening on a lot of the tasks across all of my Plan.. so It must be some
setting that I am missing - Any ideas????
 
J

Jan De Messemaeker

Hi,

Project doesn't know what a day is - you have to define it in tools,
options, calendar.
I'm sure that figure is not consistent with the working hours in tools,
change working time (whçich are the base for the planning)
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 