Day count down

D

David B

I have a 75 day project and on the bottom tier of my timescale I have the
project day count down 4, 3, 2, 1.... from end and the numer of days is
shown at 76 (start) and the begining of day 1 is shown as the end day. The
number of days counting from 1 to 75 does not have this problem. How can I
fix this to show the project ending on the end of day 1, or 0 time left?
 
J

JulieS

Hello David,
What time of day does your project end? You may also see if
changing the layout -- round to whole days setting helps. See
Format > layout.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
D

David B

The format is already set to round to whole days.

My project ends at 5am. I'm guessing this is the problem. I'll have to
figure out how to change the starting time on the activities.

Thanks
 
J

JulieS

Hi David,

If the tasks ends at 5:00 am I'm guessing you are using a 24 hrs.
calendar?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
D

David B

Yes ma'am, I am using a 24hr calendar; it is my default calendar on all of my
schedules / activities since our endeavors run 24 hrs / day.
 
D

David B

Haven't figured it out yet. My project still ends at the end of day two /
beginning of day one and not at zero. It has to be something I did wrong at
the very beginning. I'm wondering if I can export to excel and import to a
new project with just the activities and relationships? Perhaps that would
correct the timescale issue.

I'm good in Primavera and I'm being forced into using Project and it's
driving me nuts.

Thanks for your help :)
 
J

JulieS

Hmm. That does sound odd. If you go to Project > Project
Information does the calculated end date show the same date/time
as the last task?


Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
S

Steve House

I suggest you reconsider using the 24-hour calendar. While your operation
might go 24/7 it's highly unlikely that an individual person in your
resource team works like that. Tasks usually represent the work done by a
single individual or a team of individuals who work the side-by-side for the
same hours. By using the 24-hour calendar, you are saying that when poor
old Joe Resource starts working on his next task, a task with a duration of
5 day let us say, he won't get a break, a meal period or even a nap, get to
see his kids, for an entire week until the task is done. While you may very
well have work going on around the clock, when you examine the individual
tasks, work starts and stops as the resources come and go at the start and
end of their shifts. If you have some tasks going on during the day shift
and similar tasks on the swing shift, even if they are tasks on the same
component, they should be split up and managed separately rather than
lumping the work together into one task.

Even if you choose not to take the task breakdown into that much detail,
consider a task that is able to start Monday morning and requires 24
man-hours of work to complete. You have three shifts covering the 24-hour
day; day, swing, and grave. If you assign ONE worker, Joe Dayshift, the
task will start Monday and finish the end of the day Wednesday, stopping
while Joe goes home Monday and Tuesday nights. If TWO workers, Joe and
either Bill Swing or Suzie Grave, the task will end the finish the end of
the day Tuesday, running Mon day, Mon evening or Tue early morning, and then
Tue day until we've worked a total of 24 man-hours split between the two
resources. If you assign THREE workers, one from each shift, the task will
start Mon morning and end Tue morning, the total time being the result of
one shift's worth of work from each person. But in no case will the 24-hour
calendar give you this result. What you need in order to accurately model
the physical reality is the combined results of three separate calendars
describing the work hours for each of the three shifts involved in doing the
work.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top