J
JeremyE
I have tasks with one resource (JE) working at 100% (units). When I set input the hours worked (actual) for a task and then set the remaining hours to zero, it sets the task to 100% complete, but in the Gantt Chart, under the "Resource Names" column, it is displaying "JE[300%]" or "JE[26%]". Why is it doing this? Before completing the task it is set to 100% for that resource.
For example, the one with 300% next to it is a task that I estimated to take 2 hours, I entered in actual work of 2.5 hours, which effectively completed the task and set it to 100% complete. Then I look at the Gantt Chart and under Resource Names (or if I split the window to view resource details) it shows Units=300% and Work=2.5 hours.
To fix this, I am just setting the units back to 100% manually, but why is it doing this? Weird...
Thanks!!!
For example, the one with 300% next to it is a task that I estimated to take 2 hours, I entered in actual work of 2.5 hours, which effectively completed the task and set it to 100% complete. Then I look at the Gantt Chart and under Resource Names (or if I split the window to view resource details) it shows Units=300% and Work=2.5 hours.
To fix this, I am just setting the units back to 100% manually, but why is it doing this? Weird...
Thanks!!!