Developing New Schedule - Setting Dependencies

P

ProjectUser

Which is better practice: to set dependencies task-task only? or is it ok to
set dependencies tasks to WBS elements?

Thanks,
 
J

Jim Aksel

Task to Task is preferred with "Finish To Start" predecessor relationships
among them.
--
If this post was helpful, please consider rating it.

Jim
It's software; it's not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 