Disable adding a new task in MSP

P

Pallavi Jain

Hi,

I have a query.
I have say 10 tasks in my microsoft project.User canmake changes to any of
these tasks. However, I would want to disable the ability to add a new task
here.Could anyone please let me know if there is an option how we can do this?

Disabling of adding a new record/task/row in MSP.

Thanks much in advance,
Pallavi.
 
S

salgud

Hi,

I have a query.
I have say 10 tasks in my microsoft project.User canmake changes to any of
these tasks. However, I would want to disable the ability to add a new task
here.Could anyone please let me know if there is an option how we can do this?

Disabling of adding a new record/task/row in MSP.

Thanks much in advance,
Pallavi.

Project does not have that capability. I imagine it could be done with a
VBA macro, if you have someone who knows how.

Hope this helps in your world.
 