Is there a way to display duration in months instead of the traditional days?
As you can guess we have some very long projects underway and someone always
wants a different spin on things.
 
S

Steve House

As Jan said, but note that the number of months displayed won't correspond
exactly to normal calendar months, ie, a 3-month task starting 01 July won't
finish 30 September. At the default settings 3 months = 60 working days =
480 working hours = 28800 working minutes. Starting 0800 01 July the
3-month task would finish on whatever date and time where 28800 minutes of
working time as defined by the project or resource calendar will have
elapsed.
 