I have a hammock task. I see the indicator where I know I have something
linked, but I can't remember what I linked it to. How do I track down and
display what field I am linked to?

Thanks,
Mike
 
J

JulieS

Hi Mike,

Double click on the hammock task's linked start or finish date. It will
select the source task's start or finish date. I'd then stick a note on
the hammock task with the information.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information