I was wondering if there is any way not to include certain tasks in the
Critical path calculation. At the end of our project we have closeout
activities that have to take place after the mission is accomplished but
these activities are charged to different monies. Therefore, the customer
does not want them included in the critical path calculation that project
shows. But these activities are successors to the actual mission so I don't
know how to link them (for our purposees) but not include them when we
calculate CP for our customers. Any help would be appreciated.
Thanks in advance!
I was wondering if there is any way not to include certain tasks in the
Critical path calculation. At the end of our project we have closeout
activities that have to take place after the mission is accomplished but
these activities are charged to different monies. Therefore, the customer
does not want them included in the critical path calculation that project
shows. But these activities are successors to the actual mission so I don't
know how to link them (for our purposees) but not include them when we
calculate CP for our customers. Any help would be appreciated.