Don't want certain tasks in Critical Path

J

Jenn

Hi.
I was wondering if there is any way not to include certain tasks in the
Critical path calculation. At the end of our project we have closeout
activities that have to take place after the mission is accomplished but
these activities are charged to different monies. Therefore, the customer
does not want them included in the critical path calculation that project
shows. But these activities are successors to the actual mission so I don't
know how to link them (for our purposees) but not include them when we
calculate CP for our customers. Any help would be appreciated.
Thanks in advance!
 
M

Mike Glen

Hi Jenn,

Welcome to this Microsoft Project newsgroup :)

I suggest you create a new project for the post-project activities in this
case.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
M

Mike Glen

Well, you make a second Project and then consolidate them into a Master
project.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top