Duration, Actual Work and Remaining Work

O

oscar

I have set up my base project. example duration is 2 days, Remaining Work is
32hrs for 2 people. The actual Work is 60hrs. Question: How do I show that
the hrs went over the estimated hrs?
 
J

Jan De Messemaeker

Hi,

You should have taken a baseline through Tools,Tracking, Save baseline.
The Tracking Gantt together with the Variance Table show the diifferences
between actuals (and updated plan) versus baseline (the original plan)
HTH
 