Barny Blue
I have understood most of the comments so far on fixed durations, etc. but
maybe someone can help me with this.
I have one task which is going to take 300 hours. I have entered this as a
fixed work task with a duration of 300 hours. Then I assign resources, there
are three and each has their own working calendar (one is a part time
worker). Project seems to be assigning each worker an equal share of the of
the work whereas I want to have the shortest possible duration - so my full
time resources should take a larger percentage of the task, right?? Wrong??
I have tried specifying fixed units, etc. but that all goes horribly wrong -
what I need to do is specify the work first, then specify the units and let
project calcuate the duration. How can I fix work and units?
thanks for any help,
Barny
maybe someone can help me with this.
I have one task which is going to take 300 hours. I have entered this as a
fixed work task with a duration of 300 hours. Then I assign resources, there
are three and each has their own working calendar (one is a part time
worker). Project seems to be assigning each worker an equal share of the of
the work whereas I want to have the shortest possible duration - so my full
time resources should take a larger percentage of the task, right?? Wrong??
I have tried specifying fixed units, etc. but that all goes horribly wrong -
what I need to do is specify the work first, then specify the units and let
project calcuate the duration. How can I fix work and units?
thanks for any help,
Barny