B
Bob
Hi,
I'm new to Project so please go easy on me.
I am working on a software consulting project where I have to do things like research possibilities, estimate costs, propose solutions, develop software, install and configure etc.
I need to enter into Project how much actual time each task will take to figure out how much to charge AND I need to enter into Project the actual time elapsed to figure out how long it will take.
These times will be different because I wont be working on them all the time.
For instance research possibilities, estimate costs, propose solutions will happen over a 3 week period but the actual time spent doing them will amount to about 10 hours. (its a small project)
Any pointers on how I can go about this. I have tried with columns like Actual Work and Duration but altering one changes the other.
I feel I'm missing the point but I'm not sure where.
Thanks
Bob
I'm new to Project so please go easy on me.
I am working on a software consulting project where I have to do things like research possibilities, estimate costs, propose solutions, develop software, install and configure etc.
I need to enter into Project how much actual time each task will take to figure out how much to charge AND I need to enter into Project the actual time elapsed to figure out how long it will take.
These times will be different because I wont be working on them all the time.
For instance research possibilities, estimate costs, propose solutions will happen over a 3 week period but the actual time spent doing them will amount to about 10 hours. (its a small project)
Any pointers on how I can go about this. I have tried with columns like Actual Work and Duration but altering one changes the other.
I feel I'm missing the point but I'm not sure where.
Thanks
Bob